- General criteria:
- Location: the solid waste treatment Complex, Hoa Khanh Nam ward, Lien Chieu district, Da Nang city;
- Total Area: ≤ 07ha. Priotize land-saving technologies;
- Capacity: 1,000 ton/day, be able to increase capacity, expand scale of the project if necessary;
- Investment form: Public – Private Partnership (PP);
- Operation duration of the project: no more than 25 years from the date the Investor signs the project contract with a competent state agency.
- Criteria on treatment Technology:
- Compatible with natural conditions of the site;
- Compatible with characters, nature and components of domestic solid waste (including sorted and not sorted domestic solid waste);
- 100% new technology lines, machines and equipment, prioritize technology originated from developed countries (G7, EU) and listed on the Vietnam’s list of technologies encouraged for transfer or technologies certified by functional organizations and agencies;
- Encourage technologies with natural resources circulation character (take all the value of waste to renew resources) and minimum use of manufacturing materials (electricity, water…);
- The rate of waste going to landfill is ≤ 5% the total amount of domestic solid waste brought to the plant;
- Have secondary waste treatment plan, restrict burying;
- Deploy technology transfer as prescribed;
- Have plans to prevent and recover as soon as technical or environmental incidents occur.
- Criteria on Economy – Society
- Ensure the equity ratio of investors according to the current regulations;
- Service fee for domestic solid waste treatment ≤ 25 USD/ 1 ton of waste (foreign currency rates are determined according to the rate of Vietcombank), included VAT and costs of generated secondary waste.
- Criteria on capability and experience of the investor
- Investors must be experienced in construction investing and operating Domestic solid waste treatment Plant projects with capacity more than 500 ton/day in Viet Nam or other countries;
- Time duration for project construction (from the date the Investor signs the project contract with a competent state agency to the date the project officially operates): ≤ 2 years.
- Vietnamese version, download here