- What are the conditions for submitting an evaluation of detailed planning adjustment tasks to the construction planning management agency?
- The subject: the project investor approved by the competent authority according to regulations.
- The planning belongs to investment projects on the construction of works for business purposes.
- Planning is under the approval authority of the City People's Committee.
“In case a construction project of less than 5 ha is executed by one single investor (under 2 ha in case it is an apartment building project), a construction project must be formulated without formulation of detailed construction planning”; (Clause 5 Article 10 Decree 44/2015/ND-CP)
In case of adjusting the overall planning, approval of the City People's Committee is required.
In case of partial planning adjustment, steps for establishing planning tasks are not specified.
Please refer to the Danang City Administrative Procedures Information System website for more details.
- What are the procedures for detailed planning approval?
- The order of execution
+ The investor sends the appraisal dossier of tasks and detailed planning adjustment tasks to the construction planning management agency under the district People's Committee.
+ After reviewing the valid dossier, the planning management agency receives the dossier and organizes the appraisal according to the prescribed deadline.
- How to execute
How to submit | Time limits | Fees | Detail |
Directly at the Receiving and Returning Results Department of the District People's Committee | 15 or 20 days | Calculated according to project scale (according to Circular 05/2017/TT-BXD dated April 5, 2017, of the Ministry of Construction guiding the determination and management of costs associated with construction planning and urban planning) | For evaluation according to the Law on Urban Planning and Decree No. 37/2010/ND-CP Total administrative procedure implementation time: 35 working days (time limits for evaluation are 20 days, time limits for approving are 15 days) For evaluation according to the Law Construction and Decree No. 44/2015/ND-CP Total administrative procedure implementation: 30 working days (time limits for evaluation are 15 days, time limits for approving are 15 days) |
Via postal service to the Receiving and Returning Department of the District People's Committee | 15 or 20 days | Calculated according to project scale (according to Circular 05/2017/TT-BXD dated April 5, 2017, of the Ministry of Construction guiding the determination and management of costs associated with construction planning and urban planning) | For evaluation according to the Law on Urban Planning and Decree No. 37/2010/ND-CP Total administrative procedure implementation time: 35 working days (time limits for evaluation are 20 days, time limits for approving are 15 days) For evaluation according to the Law Construction and Decree No. 44/2015/ND-CP Total administrative procedure implementation: 30 working days (time limits for evaluation are 15 days, time limits for approving are 15 days) |
Please refer to the Danang City Administrative Procedures Information System website for more details.
- What are the components of the dossier when performing procedures for the evaluation of detailed planning adjustment tasks?
For evaluation of tasks and detailed planning adjustment tasks (according to the Law on Urban Planning and Decree No. 37/2010/ND-CP), the dossier includes:
Documents | Quantity |
(1) A Written request for evaluation and approval | Originals: 2 – Copies: 0 |
(2) An explanation of the contents of the task | Originals: 2 – Copies: 0 |
(3) A draft decision to approve the task | Originals: 2 – Copies: 0 |
(4) Miniature color drawings | Originals: 2 – Copies: 0 |
(5) Relevant legal documents. | Originals: 2 – Copies: 0 |
- How to execute: Directly at the District People's Committee Receiving and Returning Results Department or online.
- Receiving unit: Receiving and Returning Results Department of the district People's Committee.
- Processing Time:
+ Functional area planning:
- Time limits for evaluating: 15 days from the date of receipt of complete and valid dossiers.
- Time limits for approving: 10 days from the date of receipt of complete and valid dossiers.
+ Urban planning:
- Time limits for evaluating: 20 days from the date of receipt of complete and valid dossiers.
- Time limits for approving: 15 days from the date of receipt of complete and valid dossiers.
Please refer to the Danang City Administrative Procedures Information System website for more details.
- What are the components of the dossier when performing procedures for the evaluation of detailed planning adjustment tasks for construction special purpose zone planning and rural residential areas?
For evaluation of tasks and detailed planning adjustment tasks for construction of special purpose zone planning and rural residential areas (according to the Law on Construction and Decree No. 44/2015/ND-CP), the dossier includes:
Documents | Quantity |
A Written request for evaluation and approval | Originals: 2 – Copies: 0 |
An explanation of the contents of the task | Originals: 2 – Copies: 0 |
A draft decision to approve the task | Originals: 2 – Copies: 0 |
Miniature color drawings | Originals: 2 – Copies: 0 |
Relevant legal documents | Originals: 2 – Copies: 0 |
A written explanation of comments from agencies, organizations and residential communities on planning tasks | Originals: 2 – Copies: 0 |
Legal and qualification records of construction planning consultant | Originals: 2 – Copies: 0 |
- How to execute: Directly at the District People's Committee Receiving and Returning Results Department or online.
- Receiving unit: Receiving and Returning Results Department of the district People's Committee.
- Processing Time:
+ Special purpose zone planning:
- Time limits for evaluating: 15 days from the date of receipt of complete and valid dossiers.
- Time limits for approving: 10 days from the date of receipt of complete and valid dossiers.
+ Urban planning:
- Time limits for evaluating: 20 days from the date of receipt of complete and valid dossiers.
- Time limits for approving: 15 days from the date of receipt of complete and valid dossiers.
Please refer to the Danang City Administrative Procedures Information System website for more details.